In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the: Multiple Choice: O mean time. O marginal time. O mode time. O most likely time. O median time.

+2
Answers (1)
  1. 14 July, 00:39
    0
    Most likely time

    Explanation:

    Related concepts to understand the problem.

    In the probabilistic approach to project network analysis the most likely time is the best estimate of the time required to complete an objective (m) or a path (M), supposing everything proceeds as usual.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the: Multiple Choice: O mean ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.