PERT and CPM

a. have been combined to develop a procedure that uses the best of each.

b. have different features and are not applied to the same situation.

c. do not require a chronological relationship among activities.

d. are most valuable when a small number of activities must be scheduled.

+2
Answers (1)
  1. 6 February, 14:25
    0
    Answer is option a, i. e. have been combined to develop a procedure that uses the best of each.

    Explanation:

    In project management, PERT i. e. project evaluation and review technique is used as a statistical tool that is used to assess the overall work that is done to complete a certain project. In order to complete a particular task, there can be 'n' number of paths or ways. The best decision of selecting a pathway that is time-saving as well as cost-saving is to be found out. This chosen path is then referred to as 'Critical path.' Hence, PERT and CPM can be understood as two faces of a single coin, and have been combined to develop a procedure that uses the best of each.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “PERT and CPM a. have been combined to develop a procedure that uses the best of each. b. have different features and are not applied to the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers