A project under consideration has an internal rate of return of 15% and a beta of 0.6. The risk-free rate is 5%, and the expected rate of return on the market portfolio is 15%. a. What is the required rate of return on the project?

+1
Answers (1)
  1. 9 January, 12:55
    0
    11%

    Explanation:

    Data provided in the question:

    Internal rate of return = 15%

    Beta = 0.6

    Expected rate of return on the market portfolio = 15%

    Now,

    Required return

    = Risk-free rate + Beta * (Expected rate of return on market - Risk-free rate)

    = 5% + 0.6 * (15% - 5%)

    = 5% + 0.6 * (10%)

    = 5% + 6%

    = 11%

    Hence,

    The required rate of return on the project is 11%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A project under consideration has an internal rate of return of 15% and a beta of 0.6. The risk-free rate is 5%, and the expected rate of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.