In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?

+5
Answers (1)
  1. 19 June, 15:29
    0
    The early finish time for activity T is 29

    Explanation:

    Activity time for T is 7

    Assuming the early start time is 22,

    Early finish time = 22 + 7 = 29
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.