How Hard The Day, Inc. makes a product that has the following direct labor standards: Standard direct labor-hours 1.4 hours per unit Standard direct labor rate $ 12.00 per hour The company budgeted for production of 5,400 units in January, but actual production was 5,500 units. The company used 6,800 direct labor-hours to produce this output. The actual total direct labor cost was $82,960. The direct labor efficiency variance for January is:

+2
Answers (1)
  1. 24 February, 09:30
    0
    Direct labor time (efficiency) variance = $10,800 favorable

    Explanation:

    Giving the following information:

    Standard direct labor-hours 1.4 hours per unit

    Standard direct labor rate $ 12.00 per hour

    Actual production was 5,500 units.

    The company used 6,800 direct labor-hours to produce this output.

    To calculate the direct labor efficiency variance, we need to use the following formula:

    Direct labor time (efficiency) variance = (Standard Quantity - Actual Quantity) * standard rate

    Standard quantity = 5,500*1.4 = 7,700

    Direct labor time (efficiency) variance = (7,700 - 6,800) * 12

    Direct labor time (efficiency) variance = $10,800 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “How Hard The Day, Inc. makes a product that has the following direct labor standards: Standard direct labor-hours 1.4 hours per unit ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.