Lava Excavators, Inc., needs a drill to continue its operations and orders one for $3,000 from Mining Supplies Company. Lava tells Mining that it must receive the drill by Tuesday or it will lose $10,000. Mining ships the drill late. Lava can recover

a. $13,000.

b. $10,000.

c. $3,000.

d. $0.

+1
Answers (1)
  1. 30 December, 06:50
    0
    B) $10,000

    Explanation:

    In contract law, consequential damages are damages that the plaintiff can prove were caused by the defendant's failure to perform. Consequential damages are not limited to the amounts included in the contract.

    In this case, Lava Excavators lost $10,000 because Mining Supplies didn't deliver the drill on time.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Lava Excavators, Inc., needs a drill to continue its operations and orders one for $3,000 from Mining Supplies Company. Lava tells Mining ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers