Cranford Company completed and transferred out 3,000 units in May 2016. There were 100 units in the Work-in-Process Inventory on May 31, 2016, 40% complete as to conversion costs and 100% complete as to materials. The month's charges for conversion costs and material costs were $12,160 and $9,920, respectively. There was no beginning inventory on May 1, 2016. What is the cost of the work transferred-out during May

+5
Answers (1)
  1. 13 July, 09:36
    0
    The cost of the work transferred-out during May is $21,600

    Explanation:

    Cranford Company completed and transferred out 3,000 units in May 2016. There were 100 units in the Work-in-Process Inventory on May 31, 2016, 40% complete as to conversion costs, 100% complete as to materials.

    Material costs per unit = $9,920/3,100 = 3.2

    Conversion costs of work transferred-out = $12,160 / (3,000 + 100x40%) x3,000 = $12,000

    The cost of the work transferred-out during May = Material costs + Conversion costs = $3.2 x 3,000 + $12,000 = $21,600
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Cranford Company completed and transferred out 3,000 units in May 2016. There were 100 units in the Work-in-Process Inventory on May 31, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.