Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $90,000, variable manufacturing overhead of $3.70 per direct labor-hour, and 50,000 direct labor-hours. The company recently completed Job M800 which required 150 direct labor-hours.

The predetermined overhead rate is closest to:

a. $1.80 per direct labor-hour

b. $5.50 per direct labor-hour

c. $9.20 per direct labor-hour

d. $3.70 per direct labor-hour

+2
Answers (1)
  1. 12 December, 23:33
    0
    b. $5.50 per direct labor-hour

    Explanation:

    The computation of the predetermined overhead rate is shown below:

    = (Total estimated manufacturing overhead) : (estimated direct labor-hours)

    where,

    Total estimated manufacturing overhead = Total fixed manufacturing overhead cost + variable manufacturing overhead per direct labor hour * direct labor hours

    = $90,000 + $3.70 * 50,000 direct labor hours

    = $90,000 + $185,000

    = $275,000

    And, the direct labor hour is 50,000

    So, the predetermined overhead rate is

    = $275,000 : 50,000 direct labor hours

    = $5.50 per direct labor-hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.