A company estimates that an average-risk project has a WACC of 10 percent, a below-average-risk project has a WACC of 8 percent, and an above-average-risk project has a WACC of 12 percent. Which of the following independent projects should the company accept?

A) Project A has average risk and an IRR = 9 percent.

B) Project B has below-average risk and an IRR = 8.5 percent.

C) Project C has above-average risk and an IRR = 11 percent.

D) All of the projects above should be accepted.

E) None of the projects above should be accepted.

+3
Answers (1)
  1. 3 January, 08:09
    0
    B) Project B has below-average risk and an IRR = 8.5 percent.

    Explanation:

    Since the evaluation is based on IRR, use IRR rule that says you accept a project if its IRR > Cost of capital (WACC in this case)

    Project A's IRR of 9% is < 10% WACC for average risk projects hence reject it.

    Project B's IRR of 8.5% is > 8% WACC for below - average risk projects hence accept it.

    Project C's IRR of 11% is < 12% WACC for above - average risk projects hence reject it.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A company estimates that an average-risk project has a WACC of 10 percent, a below-average-risk project has a WACC of 8 percent, and an ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.