Canfield Construction applies overhead to its projects at a rate of $65 per direct labor hour. Laborers are paid an average rate of $30 per hour. The Jefferson Apartments project was charged a total of $1,200,000 in direct materials and $450,000 in direct labor costs. Overhead applied to the Jefferson Apartments project amounted to: (A) $450,000. (B) $650,000. (C) $975,000. (D) $1,600,000.

+3
Answers (1)
  1. 28 September, 21:03
    0
    (C) $975,000

    Explanation:

    The computation of the overhead applied is shown below:

    = Direct labors hours * rate per direct labor hour

    = 15,000 hours * $65

    = $975,000

    The direct labor is computed below:

    = Total direct labor cost : Average rate per hour

    = $450,000 : $30 per hour

    = 15,000 direct labor hours

    Hence, the correct option is c. $975,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Canfield Construction applies overhead to its projects at a rate of $65 per direct labor hour. Laborers are paid an average rate of $30 per ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.