Ask Question
23 September, 18:39

Lowden Company has an overhead application rate of 160% and allocates overhead based on direct material cost. During the current period, direct labor cost is $61,000 and direct materials used cost $79,000. Determine the amount of overhead Lowden Company should record in the current period.

a) $49,375.

b) $38,125.

c) $79,000.

d) $126,400.

e) $61,000

+2
Answers (1)
  1. 23 September, 19:44
    0
    =$126,400.00

    Explanation:

    Overhead application rate: 160 per cent on direct material cost

    Direct labor cost : $ 61,000

    Direct materiel cost: $ 79,000

    Overhead cost = 160 per cent of $ 79,000.00

    = $79,000x1.6

    =$126,400.00
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Lowden Company has an overhead application rate of 160% and allocates overhead based on direct material cost. During the current period, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers