is the amount of time an activity can be delayed from its early start without delaying the planned project finish date. a. Free float b. Forward pass c. Backward pass d. Total slack

+3
Answers (1)
  1. 21 December, 17:21
    0
    a. Free float

    Explanation:

    Free float is defined as activities that are not on the critical path of project completion. There is usually a difference between their early start date and late start date.

    These activities can be delayed without impacting on the project finish date.

    Float is also called slack, and involves 3 tyoes: total float (difference between finsihing date of the last item on critical path and project closing date), negative float (when the expected end date of last activity is after the project closing date), and free float.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “is the amount of time an activity can be delayed from its early start without delaying the planned project finish date. a. Free float b. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers