Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $42,200; design $556,000; and construction oversight $124,200. The cost drivers and estimated use are as follows. Activities Cost Drivers Expected Use of Cost Driver/Activity

Initial concept formation Number of project changes 15

Design Square feet 138,000

Construction oversight Number of months 105

Compute the predetermined overhead rate for each activity.

+2
Answers (1)
  1. 24 June, 17:36
    0
    The predetermined overhead rate for each activity.

    Activities: Initial concept formation $42,200;

    Cost Drivers: Number of project changes

    Expected Use of Cost Driver/Activity = 15

    Predetermined overhead rate for activity = Overhead/Cost Driver = 42,200 / 15 = $2813

    Activities: Design $556,000;

    Cost Drivers : Square feet

    Expected Use of Cost Driver/Activity = 38,000

    Predetermined overhead rate for activity = Overhead/Cost Driver = 556,000 / 38,000 = $ 14.63

    Activities: Construction oversight $124,200.

    Cost Drivers: Number of months

    Expected Use of Cost Driver/Activity = 105

    Predetermined overhead rate for activity = Overhead/Cost Driver = 124,220 / 105 = 1183.04
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.