Cantor Co. purchased a coal mine for $2,000,000. It cost $500,000 to prepare the coal mine for the extraction of the coal. It was estimated that 750,000 tons of coal would be extracted from the mine during its useful life. Cantor planned to sell the property for $100,000 at the end of its useful life. During the current year, 15,000 tons of coal were extracted and sold. What would Cantor's depletion amount be per ton for the current yea

+5
Answers (1)
  1. 8 March, 06:41
    0
    Depletion cost for current year $ 48,000

    Explanation:

    Computation of depletion amount

    Purchase cost $ 2,000,000

    Preparation cost $ 500,000

    Cost of mine $ 2,500,000

    Sale value at end of period $ (100,000)

    Depletion basis of mine $ 2,400,000

    Total estimated extraction from mine 750,000 tons

    Cost of extraction per ton ($ 2,400,000 / 750,000) $ 3.20 per tons

    Extraction during year 15,000 tons

    Depletion cost for the year $ 48,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Cantor Co. purchased a coal mine for $2,000,000. It cost $500,000 to prepare the coal mine for the extraction of the coal. It was estimated ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.