Sawyer Company had the following information for the year: Direct materials used$197,700 Direct labor incurred (7,600 hours) $248,100 Actual manufacturing overhead incurred$273,300 Sawyer Company used a predetermined overhead rate using estimated overhead of $382,500 and 8,500 estimated direct labor hours. Assume the only inventory balance is an ending Finished Goods balance of $9,400. How much overhead was applied during the year

+3
Answers (1)
  1. 23 September, 02:30
    0
    Allocated MOH = $342,000

    Explanation:

    Giving the following information:

    Sawyer Company used a predetermined overhead rate using estimated overhead of $382,500 and 8,500 estimated direct labor hours.

    Actual direct labor hours = 7,600

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 382,500/8,500 = $45 per direct labor hour

    Now, we can allocate overhead:

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 45*7,600 = $342,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sawyer Company had the following information for the year: Direct materials used$197,700 Direct labor incurred (7,600 hours) $248,100 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.