Ask Question
23 August, 10:19

Wexell Framing's cost formula for its supplies cost is $1,230 per month plus $10 per frame. For the month of October, the company planned for activity toward 592 frames, but the actual level of activity was 597 frames. The actual supplies cost for the month was $7,050. The activity variance for supplies cost in October would be closest to

+4
Answers (1)
  1. 23 August, 12:40
    0
    Activity variance = $150 favorable

    Explanation:

    Giving the following information:

    Standard:

    Fixed costs = $1,230

    Variable cost per unit = $10

    Actual:

    The actual level of activity was 597 frames.

    The actual supplies cost for the month was $7,050.

    To calculate the activity variance, we need to use the following formula:

    Activity variance = actual costs - standard cost*actual activity

    Standard costs = 1,230 + 10*597 = 7,200

    Activity variance = 7,050 - 7,200

    Activity variance = $150 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Wexell Framing's cost formula for its supplies cost is $1,230 per month plus $10 per frame. For the month of October, the company planned ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers