Ask Question
29 October, 11:48

The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?

Select an answer:

fast-track

assign more experienced people to tasks on the critical path

crash the schedule

cut scope

+2
Answers (1)
  1. 29 October, 12:05
    0
    Crash the schedule.

    Explanation:

    Fast-track can complete the task earlier but takes more money. Assign more experienced people will cost the management more money. Cut scope reduces the project requirement and finishes the task earlier. Therefore, options A B and D can not be the answer.

    Crash the schedule (option C) is the answer because it allocates enough resources to complete the task earlier without spending more money.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers