Four basic steps are used in an ABC system. List the proper order of these steps, which are currently scrambled below:a. Identify the primary activities and estimate a total cost pool for each. b. Allocate the costs to the cost object using the activity cost allocation rates. c. Select an allocation base for each activity. d. Calculate an activity cost allocation rate for each activity. A) c, a, b, dB) a, c, d, bC) b, a, c, dD) a, d, c, b

+4
Answers (1)
  1. 21 August, 15:34
    0
    B) a, c, d, b

    Explanation:

    a. Identify the primary activities and estimate a total cost pool for each.

    c. Select an allocation base for each activity.

    d. Calculate an activity cost allocation rate for each activity

    b. Allocate the costs to the cost object using the activity cost allocation rates
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Four basic steps are used in an ABC system. List the proper order of these steps, which are currently scrambled below:a. Identify the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers