Hushovd Iron Works has collected the following data for its Thunderbolt line of products:Direct materials standard10 pounds per unitDirect materials standard cost$0.75 per poundActual direct materials used40,000 poundsActual finished goods produced4,500 unitsWhat is the direct materials quantity variance? A) $3,750 unfavorableB) $3,750 favorableC) $6,750 unfavorableD) $6,750 favorable

+2
Answers (1)
  1. 10 May, 17:48
    0
    Direct material quantity variance = 3746.25 pounds (favorable)

    Explanation:

    Giving the following information:

    Direct materials standard 10 pounds per unit.

    Direct materials standard cost $0.75 per pound.

    Actual direct materials used 40,000 pounds.

    Actual finished goods produced 4,500 units.

    Direct material quantity variance = (standard quantity - actual quantity) * standard price

    Direct material quantity variance = (10-8.89) * 0.75 = 0.8325*4500units = 3746.25 pounds (favorable)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Hushovd Iron Works has collected the following data for its Thunderbolt line of products:Direct materials standard10 pounds per unitDirect ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.