a. A loan processing operation that processes an average of 4 loans per day. The operation has a design capacity of 12 loans per day and an effective capacity of 11 loans per day. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)

+3
Answers (1)
  1. 2 October, 07:47
    0
    Efficiency = 36.36%

    Utilization = 33.33%

    Explanation:

    The question is to determine the efficiency and the utilization for each of the situations as follows:

    First, we need to understand the formula to be used for efficiency and then for utilization.

    Efficiency formula = (The Actual Output / Effective Capacity) x 100

    Utilization Formula = (The Actula Output / Design Capacity) x 100

    Secondly, we apply the formulas as follows:

    Efficiency = Average Loans per day (4) / Effective Capacity (11) x 100

    = 4/11 x 100 = 36.36%

    Utilization = The average output (4) / Design Capacity (12) x 100

    =4/12 x 100 = 33.33%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “a. A loan processing operation that processes an average of 4 loans per day. The operation has a design capacity of 12 loans per day and an ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.