Ask Question
14 March, 19:45

The production budget for manner company shows units to be produced as follows: july, 630: august 690, and september 550. Each unit produced requires three hours of direct labor. The direct labor rate is currently $16 per hour but is predicted to be $16.75 per hour in september.

Prepare a direct labor budget for the months July, August, and September.

+2
Answers (1)
  1. 14 March, 20:05
    0
    Results are below.

    Explanation:

    Giving the following information:

    Production:

    July, 630

    August 690

    September 550

    Each unit produced requires three hours of direct labor.

    The direct labor rate is currently $16 per hour but is predicted to be $16.75 per hour in September.

    Direct labor budget July:

    Direct labor hours required = 630*3 = 1,890

    Direct labor cost = 1,890*16 = $30,240

    Direct labor budget August:

    Direct labor hours required = 690*3 = 2,070

    Direct labor cost = 2,070*16 = $33,120

    Direct labor budget September:

    Direct labor hours required = 550*3 = 1,650

    Direct labor cost = 1,650*16.75 = $27,637.5
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The production budget for manner company shows units to be produced as follows: july, 630: august 690, and september 550. Each unit ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.