If overhead is applied to individual jobs at a rate of 60% of direct labor costs incurred per job, and $40,000 in materials were used and $15,000 of direct labor was required - what was the overhead costs charged to the job?

+5
Answers (1)
  1. 18 November, 17:37
    0
    Overhead charged = $9,000

    Explanation:

    Overhead cost = 60% x $15,000

    =$9,000

    Hence, the overhead costs charged to the job = $9,000.

    Overhead costs refer to those expenses associated with running a business that can't be linked directly to a particular product or service.

    Hence, this is always apportioned to different products and services using a fair basis that represents how the costs have been consumed or utilized.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If overhead is applied to individual jobs at a rate of 60% of direct labor costs incurred per job, and $40,000 in materials were used and ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers