When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest. Group of answer choices True False

+2
Answers (1)
  1. 7 October, 22:55
    0
    False.

    Explanation:

    In a Time-Cost Model, cost is assumed to be a linear function of time. There is always a relation between project time and its associated costs. These costs can be direct or indirect depending on its nature. The best way is to find critical path is by operating a normal schedule and then reduce time according to lowest cost activity. The crash time is the shortest time allowed for each activity and this is the time in which an activity is completed.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers