Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $ 231 Direct labor $ 153 Required: 1. What is the total manufacturing cost assigned to Job A-500?

+3
Answers (1)
  1. 24 September, 06:50
    0
    Total manufacturing cost = $510

    Explanation:

    Giving the following information:

    Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $ 231 Direct labor $ 153.

    Direct labor hours = 153/17 = 9 hours

    Total manufacturing cost = direct material + direct labor + manufacturing overhead = 231+153 + (14*9) = $510
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers