Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the cost-plus price to place a bid on a community swimming pool, deck, and spa. The estimated cost associated with the new project is $225,000. The markup on the project cost is 40%. What is the cost-plus price required to bid on the new project?

+2
Answers (1)
  1. 14 February, 08:24
    0
    Price = $315,000

    Explanation:

    Giving the following information:

    The manager needs to compute the cost-plus price to place a bid on a community swimming pool, deck, and spa. The estimated cost associated with the new project is $225,000. The markup on the project cost is 40%.

    Price = 225,000 * 1.40 = $315,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers