Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters? Selected Answer:a. parametric estimatingAnswers:a. parametric estimatingb. analogous estimatingc. grass roots estimatingd. empirical estimating
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.