A project's critical path is composed of activities A (variance. 33), B (variance. 67), C (variance. 33), and D (variance. 17). What is the standard deviation on the critical path?

+3
Answers (1)
  1. 16 July, 08:22
    0
    standard deviation on the critical path is 1.22

    Explanation:

    Given the four (4) activities below,

    Activities A has Variance (.33)

    Activities B has Variance (.67)

    Activities C has Variance (.33)

    Activities D has Variance (.17)

    Hence,

    Standard Deviation = √sum of variance of activities A, B, C and D

    =√.33+.67+.33+.17

    SD = √1.5

    SD = 1.22
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A project's critical path is composed of activities A (variance. 33), B (variance. 67), C (variance. 33), and D (variance. 17). What is the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.