If the budgeted factory overhead cost is $460,000, the budgeted direct labor hours are 80,000, and the actual direct labor hours are 6,700 for the month, the amount of factory overhead to be allocated is $38,525 (if the allocation is based on direct labor hours). True/False

+2
Answers (1)
  1. 13 January, 10:20
    0
    True

    Explanation:

    For computing the amount of factory overhead amount, first, we have to compute the predetermined overhead rate. The formula is shown below:

    Predetermined overhead rate = (Total estimated manufacturing overhead) : (estimated direct labor-hours)

    = $460,000 : 80,000 hours

    = $5.75

    Now the amount of factory overhead which equal to

    = Actual direct labor-hours * predetermined overhead rate

    = 6,700 hours * $5.75

    = $38,525
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If the budgeted factory overhead cost is $460,000, the budgeted direct labor hours are 80,000, and the actual direct labor hours are 6,700 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.