The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?

+1
Answers (2)
  1. 22 February, 16:40
    0
    Fast Track
  2. 22 February, 18:22
    0
    Crash the schedule

    Explanation:

    Crashing is the method to utilize when optimizing has not spared enough time on the calendar. It is a method wherein assets are added to the venture for the least cost conceivable.

    Cost and schedule tradeoffs are broke down to decide how to acquire the best measure of pressure for the least steady cost.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers