LO 6.1Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor hours costing $2,500,000 in labor and utilizing 12,500 machine hours. Calculate the predetermined overhead rate using:

Direct labor hours

Direct labor dollars

Machine hours

+4
Answers (1)
  1. 15 October, 21:09
    0
    Instructions are listed below.

    Explanation:

    Giving the following information:

    Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor hours costing $2,500,000 in labor and utilizing 12,500 machine hours.

    For each allocation base we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Direct labor hours:

    Estimated manufacturing overhead rate = 250,000/100,000 = $2.5 per direct labor hour

    Direct labor dollars:

    Estimated manufacturing overhead rate = 250,000/2,500,000 = $0.1 per direct labor dollar

    Machine hours:

    Estimated manufacturing overhead rate = 250,000/12,500=$20 per machine hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “EA1. LO 6.1Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor hours costing $2,500,000 in ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.