Benton Engineering Services Company incurred the following during 2016 Direct labor $94,000 Overhead 126,000 Selling expenses 112,000 Administrative expenses 102,000 Calculate prime cost and conversion cost for Benton Engineering Services Company during 2016.

+2
Answers (1)
  1. 14 September, 04:10
    0
    Prime cost = $94,000

    Conversion cost = $135,400.

    Explanation:

    Prime cost is the addition of direct material cost, direct labor cost and direct expenses.

    Conversion cost is the cost of converting raw materials into finished product. It s the sum of direct labour cost and production overheads.

    For Bento Engineering,

    Prime cost = direct labour cost (since no figure is given for direct material and direct expenses.)

    Prime cost = $94,000

    Conversion cost = Direct labour cost + overheads

    Conversion cost = $94,000 + 126,000

    = $135,400.

    Prime cost = $94,000

    Conversion cost = $135,400.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Benton Engineering Services Company incurred the following during 2016 Direct labor $94,000 Overhead 126,000 Selling expenses 112,000 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.