LO 5.3Vexar manufactures nails. Manufacturing is a one-step process where the nails are forged. This is the information related to this year’s production:

Ending inventory was 100% complete as to materials and 70% complete as to conversion, and the total materials cost is $115,080 and the total conversion cost is $72,072. Using the weighted-average method, what are the unit costs if the company transferred out 34,000 units? Using the weighted-average method, prepare the company’s process cost summary for the month.

+2
Answers (1)
  1. 24 September, 11:02
    0
    The unit costs are $ 4.87 for 70 % Conversion Costs

    The unit costs are $ 5.54 for finished goods

    Explanation:

    Total Materials cost = $ 115,080

    Material Costs for one unit = $ 115,080 / 34000 = $ 3.3847 = $ 3.39

    Conversion Costs = $ 72,072

    Conversion Costs for one unit = $ 72072/34000 * 70% = $ 1.4838 = $ 1.48

    Total Cost per unit = $ 3.39 + $ 1.48 = $ 4.87

    Process Cost summary

    Quantity Schedule

    Materials = ($3.39 * 34,000) = $ 115,080

    Cost Added by Department: Total Cost Unit Cost

    Materials = $ 115,080 $ 3.39

    Conversion Costs

    Labor + Overheads (1.48 * 34,000) = $ 50,320 $ 1.48

    Units still in process ($ 72072 - $ 50320) = $ 19,752 $0.58

    Total cost to be accounted for $ 187,152 $ 5.54
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “PB3. LO 5.3Vexar manufactures nails. Manufacturing is a one-step process where the nails are forged. This is the information related to ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.