The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.