The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished

+3
Answers (1)
  1. 7 June, 10:02
    0
    The computation of the number of slacks in the project A when it is finished is

    = Total completion time - - Task A planned days - Task B planned days - Task C planned days

    = 25 days - 9 days - 5 days - 8 days

    = 3 days slack

    Simply we subtract the total planned days taken by each task from the total completion time on a project so that the number of slacks has come

    Therefore, it came positive 3 slacks time
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.