Ask Question
29 April, 12:42

Rintharamy Corporation's management reports that its average delivery cycle time is 25.2 days, its average throughput time is 7.6 days, its manufacturing cycle efficiency (MCE) is 0.25, its average move time is 0.9 day, and its average queue time is 4.0 days. Required: a. What is the wait time? (Enter your answer rounded to 1 decimal places.) b. What is the process time? (Enter your answer rounded to 1 decimal places.) c. What is the inspection time? (Enter your answer rounded to 1 decimal places.)

+3
Answers (1)
  1. 29 April, 16:13
    0
    a. 17.6 days

    b. 1.9 days

    c. 0.8 days

    Explanation:

    The computation is shown below:

    a. Wait time

    = Delivery cycle time - average throughput time

    = 25.2 days - 7.6 days

    = 17.6 days

    b. Process time

    = Manufacturing cycle efficiency (MCE) * average throughput time

    = 0.25 * 7.6 days

    = 1.9 days

    c. Inspection time

    = Average throughput time - process time - average move time - average queue time

    = 7.6 days - 1.9 days - 0.9 days - 4.0 days

    = 0.8 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Rintharamy Corporation's management reports that its average delivery cycle time is 25.2 days, its average throughput time is 7.6 days, its ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers