Krumple Inc. produces aluminum cans. Production of 12-ounce cans has a standard unit quantity of 4.7 ounces of aluminum per can. During the month of April, 450,000 cans were produced using 1,875,000 ounces of aluminum. The actual cost of aluminum was $0.10 per ounce and the standard price was $0.08 per ounce. There are no beginning or ending inventories of aluminum.

Required:Calculate the total variance for aluminum for the month of April. Enter amount as a positive number and select Favorable or Unfavorable.

+5
Answers (1)
  1. 1 September, 07:07
    0
    -$18,300 (Unfavorable)

    Explanation:

    Material price per variance:

    = Ounces of aluminium used in production (Standard price - Actual cost per ounce)

    = 1,875,000 ($0.08 - $0.10)

    = 1,875,000 * (-$0.02)

    = - $37,500 (Unfavorable)

    Material usage variance:

    = [ (Cans produced * Standard unit quantity) - Ounces of aluminium used in production] * Standard price

    = [ (4,50,000 * 4.7) - 1,875,000] * 0.08

    = $19,200 (Favorable)

    Therefore,

    Total variance = Material price per variance + Material usage variance

    = - $37,500 + $19,200

    = - $18,300 (Unfavorable)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Krumple Inc. produces aluminum cans. Production of 12-ounce cans has a standard unit quantity of 4.7 ounces of aluminum per can. During the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.