Estimated costs for activity cost pools and other item (s) are as follows: Machining $500000 Assembling 200000 Advertising 450000 Inspecting and testing 175000 Total estimated overhead isA. $875000. B. $1150000. C. $1325000. D. $700000.

+1
Answers (1)
  1. 7 August, 02:57
    0
    A) $875000

    Explanation:

    total estimated manufacturing overhead costs = machining costs + assembling costs + inspecting and testing costs = $500,000 + $200,000 + $175,000 = $875,000

    Advertising costs ($450,000) are included under sales and administrative costs, not production costs.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Estimated costs for activity cost pools and other item (s) are as follows: Machining $500000 Assembling 200000 Advertising 450000 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.