Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $3,360,000 (240,000 hours at $14/hour) and that factory overhead would be $1,540,000 for the current period. At the end of the period, the records show that there had been 220,000 hours of direct labor and $1,240,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? (Round your answer to two decimal places.)

A) $5.17 per direct labor hour.

B) $7.00 per direct labor hour.

C) $6.42 per direct labor hour.

D) $5.84 per direct labor hour.

E) $6.25 per direct labor hour.

+2
Answers (1)
  1. 26 August, 22:20
    0
    Option (C) is correct.

    Explanation:

    Given that,

    Estimated overhead cost = $1,540,000

    Estimated direct labors (in dollars) = $3,360,000

    Estimated direct labor hours = 240,000

    Actual overhead cost = $1,240,000

    Predetermined overhead rate:

    = Estimated overhead cost : Estimated direct labor hours

    = $1,540,000 : 240,000

    = $6.42 per direct labor hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $3,360,000 (240,000 hours at ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.