Which of the following is the correct mathematical representation of direct labor rate variance (LRV) ?

A. Direct labor rate variance = (Actual hourly wage rate - Standard hourly wage rate) * Actual direct labor hours used

B. Direct labor rate variance = (Standard direct labor hours allowed - Actual direct labor hours used) * Standard hourly wage rate

C. Direct labor rate variance = Actual hourly wage rate - Standard hourly wage rate

D. Direct labor rate variance = Standard direct labor hours allowed - Actual direct labor hours used

+2
Answers (1)
  1. 21 April, 06:48
    0
    Answer: not in any option

    Explanation: Labour rate variance = (standard Labour hour - actual Labour hour) * actual Labour hour.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is the correct mathematical representation of direct labor rate variance (LRV) ? A. Direct labor rate variance = ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.