Which of the following is the correct mathematical representation of direct labor rate variance (LRV) ?
A. Direct labor rate variance = (Actual hourly wage rate - Standard hourly wage rate) * Actual direct labor hours used
B. Direct labor rate variance = (Standard direct labor hours allowed - Actual direct labor hours used) * Standard hourly wage rate
C. Direct labor rate variance = Actual hourly wage rate - Standard hourly wage rate
D. Direct labor rate variance = Standard direct labor hours allowed - Actual direct labor hours used
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is the correct mathematical representation of direct labor rate variance (LRV) ? A. Direct labor rate variance = ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » Which of the following is the correct mathematical representation of direct labor rate variance (LRV) ? A. Direct labor rate variance = (Actual hourly wage rate - Standard hourly wage rate) * Actual direct labor hours used B.