What of the following kinds of contracts is the actual, final cost of the project unknown until after the project is completed (circle all that apply):
1. cost plus fixed fee
2. fixed price
3. cost plus incentive fee
4. none of these
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “What of the following kinds of contracts is the actual, final cost of the project unknown until after the project is completed (circle all ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » What of the following kinds of contracts is the actual, final cost of the project unknown until after the project is completed (circle all that apply): 1. cost plus fixed fee 2. fixed price 3. cost plus incentive fee 4. none of these