Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at $10/hour) and that factory overhead would be $1,500,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,200,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate?

+4
Answers (1)
  1. 5 December, 18:36
    0
    The predetermined over head rate was 1,500,000/200,000=$7.5 of overhead charges per hour of labor
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.