Ask Question
24 November, 22:58

How much work Must a Development Team do to select a Product Backlog item for Sprint?

A. As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of done.

B. As much as it can fit into the Sprint.

C. The best it can do given that it is usually impossible for QA to finish all of the testing that is needed to prove shippability.

D. Analysis, design, programming, testing and documentation.

+2
Answers (2)
  1. 24 November, 23:30
    0
    A

    Explanation:

    As much as it has told the Product Owner will bd done for everyProduct Backlog item it selects in conformance with the definition of done

    Ecery Sprint purpose is to deliver a certain amount of potentially releasable functionality that align to the Scrum Team's current definition of "Done".
  2. 25 November, 00:50
    0
    A

    Explanation:

    Because Team's work on item must be completed in accordance to definition of done. Scrum Guide emphasizes on a common language referring to the process must be shared by all participants and it must be definition of Done. So, for a product backlog item to select, it must fulfil definition of Done.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “How much work Must a Development Team do to select a Product Backlog item for Sprint? A. As much as it has told the Product Owner will be ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers