At the beginning of 2017, Wertz Construction Company changed from the completed-contract method to recognizing revenue over time (percentage-of-completion) for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2017, pretax income under the two methods was as follows: percentage-of-completion $120,000, and completed-contract $80,000. The tax rate is 35%. Prepare Metlock's 2017 journal entry to record the change in accounting principle.

+5
Answers (1)
  1. 29 July, 09:49
    0
    Income under completed contract = $80,000

    Tax = $28,000 (0.35*80,000)

    Income under percentage of completion = $120,000

    Tax = 0.35*120,000 = $42,000

    Income difference = 120,000-80,000 = $40,000

    Tax difference = 42,000-28,000 = $14,000

    Addition to retained earnings = 40,000-14,000 = $26,000

    Journal Entry's

    Debit Credit

    Construction Revenue $40,000

    Deferred tax liability $14,000

    Retained Earnings $26,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “At the beginning of 2017, Wertz Construction Company changed from the completed-contract method to recognizing revenue over time ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.