You are the project manager of a project that is running behind schedule. The project sponsor is very unhappy at the new finish date that you proposed, but he has accepted it. However, you also requested extra funds the support the extended time of work, and the sponsor has refused and is threatening to cancel the project if you cannot finish the project within the planned budget. What are your options?

+4
Answers (1)
  1. 15 May, 00:17
    0
    Fast tracking.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You are the project manager of a project that is running behind schedule. The project sponsor is very unhappy at the new finish date that ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.