3. Project Manager John Boy has a policy of only using experienced, dependable, and proven sellers instead of selecting sellers through open competition as a means to manage procurement risk. What risk management technique is John Boy using? A. Risk Acceptance. B. Risk Mitigation. C. Risk Transfer D. Risk Avoidance.
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “3. Project Manager John Boy has a policy of only using experienced, dependable, and proven sellers instead of selecting sellers through ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.