The King Corporation manufactures custom-made furniture. The following data pertains to Job X4A: Direct materials placed into production $9,000 Direct labor hours worked 300 hours Direct labor rate per hour $15 Machine hours worked 100 hours Plantwide overhead rate is $22.50 per machine hour. Job X4A consists of 500 units. One-half of Job X4A was sold for $10,000. What is the cost per unit for Job X4A?

+5
Answers (1)
  1. 23 January, 01:09
    0
    The answer is: The total cost per unit is $31.50

    Explanation:

    First we have to calculate the total costs for Job X4A

    Direct materials $9,000 Direct labor hours 300 x $15 per labor hours = $4,500 Machine hours 100 x $22.50 overhead rate per machine hour. = $2,250

    Total costs for Job X4A = $9,000 + $4,500 + $2,250 = $15,750

    Cost per unit = $15,750 / 500 units = $31.50
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The King Corporation manufactures custom-made furniture. The following data pertains to Job X4A: Direct materials placed into production ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.