The following information is available for a company's maintenance cost over the last seven months.
Month Maintenance Hours Maintenance Cost
June 11 $ 5,050
July 17 6,850
August 13 5,650
September 16 6,550
October 22 8,350
November 25 9,250
December 7 3,850
Using the high-low method, estimate both the fixed and variable components of its maintenance cost.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following information is available for a company's maintenance cost over the last seven months. Month Maintenance Hours Maintenance ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.