The Davis Corporation budgeted factory overhead at $250,000 for the period for the Assembly department, based on a budgeted volume of 100,000 direct labor hours. At the end of the period, the factory overhead control account for the Assembly department had a balance of $252,000. The actual (and allowed) direct labor hours were 104,000. What was the over - or underapplied factory overhead for the period?

A. $8,000 overapplied

B. $10,000 underapplied

C. $10,000 overapplied

D. $8,000 underapplied

+4
Answers (1)
  1. 13 September, 10:01
    0
    B. $10,000 Underapplied

    Explanation:

    Hourly rate = $250,000/100,000 = $2.5 per hour

    Excess hours = 4000

    Excess over head = 4000 * 2.5 = $10,000

    There was a $10,000 underapplied overhead for that period
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The Davis Corporation budgeted factory overhead at $250,000 for the period for the Assembly department, based on a budgeted volume of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers