Ask Question
9 August, 11:15

Lorenzo Company uses a job order costing system that charges overhead to jobs on the basis of direct materials cost. At year-end, the Work in Process Inventory account shows the following.

Date Explanation Debit Credit Balance

2017

Dec. 31 Direct materials cost 1,800,000 1,800,000

31 Direct labor cost 250,000 2,050,000

31 Overhead applied 612,000 2,662,000

31 To finished goods 2,572,000 90,000

1. Determine the predetermined overhead rate used (based on direct materials cost).

2. Only one job remained in work in process inventory at December 31, 2017. Its direct materials cost is $27,000. How much direct labor cost and overhead cost are assigned to this job?

+5
Answers (1)
  1. 9 August, 11:51
    0
    a. Overhead Rate = 0.34

    b. Direct Labour Cost = $53,820

    Explanation:

    a.

    Overhead Rate based on direct materials is calculated as overhead cost/direct material cost

    Overhead Cost = $612,000

    Direct Materials Cost = $1,800,000

    Overhead Rate = $612,000/$1,800,000

    Overhead Rate = 0.34

    b.

    Given

    Total cost of job in process = $90,000

    Material Cost of job in process = $27,000

    Overhead Applied = $9,180 (0.34% * $27,000)

    Direct Labour Cost = Cost of job in process - Material Cost - Overhead Applied

    Direct Labour Cost = $90,000 - $27,000 - $9,180

    Direct Labour Cost = $53,820
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Lorenzo Company uses a job order costing system that charges overhead to jobs on the basis of direct materials cost. At year-end, the Work ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers