Which of the following is the assignment process used with normal costing?
a. Actual direct materials, actual direct labor and actual overhead cost are assigned to products.
b. Actual direct labor cost is assigned to products, but direct material and overhead costs are assigned using predetermined rates.
c. Actual direct material and direct labor costs are assigned to products, but overhead costs are assigned using predetermined rates.
d. Actual direct materials cost is assigned to products, but direct labor and overhead costs are assigned using predetermined rates.
e. All of these manufacturing costs are assigned using predetermined rates.
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is the assignment process used with normal costing? a. Actual direct materials, actual direct labor and actual ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » Which of the following is the assignment process used with normal costing? a. Actual direct materials, actual direct labor and actual overhead cost are assigned to products. b.