Ask Question
15 October, 18:30

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining? (A) 4 (B) 5 (C) 6 (D) 7 (E) 8

+2
Answers (1)
  1. 15 October, 19:35
    0
    option (B) 5

    Explanation:

    Given:

    Estimated number of men required if no rain = 10

    Number of days required in there is no rain = 110

    Number of days with rain = 5

    Number of people hired after the 61st day = 6

    Therefore,

    Total man-days required = 10 * 110 = 1100

    Total Man-days before 61st day

    = (60 days - number of days with rain) * Initial number of men

    = (60 - 5) * 10

    = 550

    let the number of days it rained after day 60 be 'n'

    Thus,

    Man-days worked after 61st day

    = Total number of men after 61st day * (100 days - 60 days - x)

    = 16 * (40 - n)

    also,

    Total man-days required = Total Man-days before 61st day + Man-days worked after 61st day

    or

    1,100 = 550 + 16 * (40 - n)

    or

    550 = 640 - 16n

    or

    n = 5.625

    therefore,

    It rained for 5 days

    option (B) 5
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers